Copy this file to a per-event location (e.g., events/2025-flagship/run-of-show.md). The Producer / RoS Owner maintains this document from T-45 through T+0. The AV / Tech Lead reviews and signs off at T-7. Any change after T-7 requires both the Producer and AV Lead to initial the Notes column. Times use 24h local time.

Column reference per ../../programs/events/README.md §6: Time | Duration | Segment | Owner | Backup | Cue | Notes.


Pre-Event: T-1 Setup

The Producer and AV / Tech Lead run this table on-site the day before T-0. All rows must be checked before the team leaves for the night. Add the Volunteer Coordinator to load-in rows where crew is needed.

Time Duration (min) Task Owner Backup Cue Notes
TODO:08:00 120 Load-in: furniture, AV equipment, staging AV / Tech Lead TODO Venue access confirmed by Event Director TODO: dock access code, elevator reservation
TODO:10:00 60 AV walkthrough: mics, screens, stream test, slide advance AV / Tech Lead TODO Load-in complete TODO: streaming platform credentials
TODO:11:00 30 Signage placement: wayfinding, sponsor recognition, session rooms Volunteer Coordinator TODO AV walkthrough in progress TODO: signage kit location, layout map
TODO:11:30 30 Registration desk setup: badge stock, lanyards, check-in device Volunteer Coordinator TODO Signage underway TODO: badge printer IP, comp list
TODO:12:00 60 Green room prep: speaker AV check, water, bios posted Producer / RoS Owner TODO Registration desk live TODO: speaker arrival schedule
TODO:13:00 60 Full rehearsal: opening segment, keynote mic handoff, transitions Producer / RoS Owner TODO All leads on-site TODO: flag any slide or mic issues to AV Lead immediately
TODO:14:00 30 Volunteer briefing: roles, radio channels, emergency exits, CoC officer intro Volunteer Coordinator TODO Rehearsal complete TODO: radio channel assignments

Day 1 Run-of-Show

Producer calls each segment from the stage or green room. Owner is the on-site person responsible for starting and ending the segment. Cue is the signal the Owner watches for.

Time Duration (min) Segment Owner Backup Cue Notes
TODO:07:30 30 Registration opens — badge pickup and wayfinding Volunteer Coordinator TODO Doors unlocked by venue TODO: badge pick-up table location; flag VIPs for Producer
TODO:08:00 60 Exhibitor and sponsor setup window Sponsor Lead TODO Registration desk staffed TODO: booth assignments confirmed in advance
TODO:09:00 15 General session opens — attendees seated, pre-roll slides AV / Tech Lead TODO Producer gives "go" TODO: pre-roll deck path; music cued
TODO:09:15 30 Opening: welcome, housekeeping, sponsor acknowledgment Event Director Producer / RoS Owner Producer cue via radio TODO: slide 1 on screen; streaming start confirmed
TODO:09:45 60 Opening keynote TODO: Speaker name TODO Event Director handoff on stage TODO: slide deck loaded; lapel mic; recording running
TODO:10:45 15 Networking break — sponsor activation window Sponsor Lead TODO Keynote ends TODO: refreshment station sponsor signage live
TODO:11:00 75 Concurrent breakouts — Sessions A, B, C TODO: Room leads TODO Break ends; Producer radio cue TODO: each room lead has own mic and slide remote
TODO:12:15 60 Lunch — catered; sponsor table presence Sponsor Lead TODO Breakouts end TODO: dietary table labels; CE session not awarded during lunch
TODO:13:15 75 Concurrent breakouts — Sessions D, E, F TODO: Room leads TODO Lunch cleared; Producer cue TODO: attendance sign-in sheets active; attestation QR posted
TODO:14:30 15 Afternoon break Volunteer Coordinator TODO Breakouts end TODO: refreshment station restocked
TODO:14:45 60 General session — panel or featured talk Producer / RoS Owner TODO Break ends; attendees recalled TODO: panel mics set; moderator briefed
TODO:15:45 30 Day 1 close: recap, Day 2 preview, housekeeping Event Director TODO Panel ends TODO: slide with Day 2 agenda on screen
TODO:16:15 90 Evening reception — sponsor-named if applicable Sponsor Lead TODO General session ends TODO: reception room open; catering confirmed; badge required

Day 2 Run-of-Show

Attendance is typically lighter on Day 2. CE-awarding sessions scheduled here require the same sign-in and attestation flow as Day 1.

Time Duration (min) Segment Owner Backup Cue Notes
TODO:08:30 30 Registration re-opens — Day 2 check-in Volunteer Coordinator TODO Doors unlocked TODO: Day 2-only badges if applicable
TODO:09:00 15 General session opens — pre-roll slides AV / Tech Lead TODO Producer "go" TODO: Day 2 pre-roll deck path
TODO:09:15 45 Morning talk or workshop TODO: Speaker name TODO Producer cue TODO: slide deck; mic check before doors open
TODO:10:00 75 Concurrent breakouts — Sessions G, H TODO: Room leads TODO Morning talk ends TODO: CE sign-in sheets; attestation QR posted
TODO:11:15 15 Break Volunteer Coordinator TODO Breakouts end TODO: refreshment restocked
TODO:11:30 45 Member-led session or town hall Producer / RoS Owner TODO Break ends TODO: open-mic setup; Volunteer on crowd mic
TODO:12:15 45 Lunch — abbreviated Volunteer Coordinator TODO Session ends TODO: boxed lunch if venue permits early departure
TODO:13:00 60 Closing general session: recognition, year-ahead preview, call to action Event Director TODO Lunch ends TODO: award items at podium; CE Lead present for CE close
TODO:14:00 15 Official close — photo, final housekeeping Event Director TODO Recognition complete TODO: group photo logistics confirmed with AV Lead

Tear-Down

Producer and AV Lead run this table immediately after official close. Volunteer Coordinator retains lost-and-found until handoff.

Time Duration (min) Task Owner Backup Cue Notes
TODO:14:30 60 AV strike: disconnect, pack, label equipment cases AV / Tech Lead TODO Official close complete TODO: venue dock hours; carrier pickup confirmed
TODO:14:30 60 Exhibitor and sponsor load-out Sponsor Lead TODO Official close TODO: provide hand trucks; confirm sponsor booth count
TODO:15:30 30 Signage removal and pack Volunteer Coordinator TODO AV strike underway TODO: return venue signage if any; dispose of single-use materials
TODO:16:00 30 Lost-and-found handoff to venue manager Volunteer Coordinator TODO Signage packed TODO: photograph items before handoff; log in close-out report
TODO:16:30 30 Final venue walk-through with venue manager Event Director Producer / RoS Owner Load-out complete TODO: check for damage; get venue sign-off sheet

Hybrid Track Notes

When the event is hybrid, add two sub-columns under each time row — one for the in-room track and one for the virtual track — sharing a single Time column. The AV / Tech Lead owns the stream and must be reachable by both the in-room Producer and the virtual platform moderator at all times. The Marketing Lead confirms the Zoom / StreamYard session link is live and shared with registrants before T-0.

Mini-example of a hybrid row:

Time Duration (min) Segment In-room Owner Virtual Owner Backup Cue Notes
09:15 30 Opening welcome Event Director (on stage) Marketing Lead (on platform) Producer / RoS Owner Producer radio + Slack DM to virtual host Stream live indicator confirmed; slide deck shared to both rooms

For a fully hybrid event, replace the single Owner column in the Day 1 and Day 2 tables with separate In-room Owner and Virtual Owner columns following this pattern.


Backup Plans

The Producer / RoS Owner is responsible for activating the appropriate backup plan. All backup plans are communicated to the full team at the T-1 briefing.

  • Speaker no-show: Producer contacts speaker via phone at T-30 min. If no response by T-15 min, pull the standby speaker or extend the preceding break and announce a schedule change. Notify attendees from the stage; do not speculate on reason.
  • AV failure: AV / Tech Lead has a pre-identified fallback: laptop-to-projector direct connect, backup microphone in the green room, and hotspot for streaming. If streaming cannot be restored within 15 minutes, Producer announces the session will be recorded and distributed; in-room attendees continue.
  • Attendee medical emergency: Volunteer Coordinator calls venue emergency line and 911 immediately. Safety / CoC Officer clears a path. Producer continues or pauses program at their discretion based on severity; do not announce medical details over PA. Document in close-out report under Incidents.
  • Weather or venue issue: Event Director makes the go/no-go call. If the venue is evacuated, Producer directs attendees to the pre-designated rally point communicated during morning housekeeping. Reassemble when venue gives all-clear.
  • Virtual platform outage: AV / Tech Lead switches to backup platform (pre-configured credentials held by AV Lead and Marketing Lead). Marketing Lead sends attendee notification within 5 minutes. Session may be delayed up to 20 minutes before Producer calls a reschedule.
  • Fire alarm: All staff treat as real until venue confirms otherwise. Volunteer Coordinator leads attendees to exits. Do not retrieve equipment. Document in close-out report.
  • Late VIP or keynote speaker: Producer fills time with a Q&A or facilitated discussion. Do not announce the delay as a problem; frame as an extended networking or discussion period. Notify Event Director immediately.

AV Lead Sign-Off (T-7)

Field Value
AV Lead name TODO
Sign-off date TODO: (must be at or before T-7)
Outstanding items at sign-off TODO: (list any; "None" if clean)